KRMA News

January Monthly Report
by Edie Surprenant
Monday, 25 February 2008

KRMA's January Highlights

Read More...


August Monthly Report
Thursday, 17 January 2008

KRMA’S AUGUST HIGHLIGHTS

In August, Triple R Equipment began working on Final Clarifier #4. They will be rebuilding, abrasive blasting and re-coating the driveassembly, replacing...

Read More...


September Monthly Report
Thursday, 17 January 2008

KRMA’S SEPTEMBER HIGHLIGHTS

Strand Associates is working on the design for the replacement plan for the SCADA (supervisory control and data acquisition) system. The SCADA system...

Read More...


October Monthly Report
Thursday, 17 January 2008

KRMA’S OCTOBER HIGHLIGHTS

During October, KRMA Staff continued to work with MidAmerican Energy and ComEd representatives to clarify the electric charges by MidAmerican Energy to...

Read More...


November Monthly Report
Thursday, 17 January 2008

KRMA’S NOVEMBER HIGHLIGHTS

During November, BC Systems rebuilt the air dryer in the Generator Building #65. Earlier this year, the air dryer in the Generator Building #65 was...

Read More...


December Monthly Report
Thursday, 17 January 2008

KRMA’S DECEMBER HIGHLIGHTS

During December, Joliet Boiler and Welding Co. repaired the generator heat exchanger. The work consisted of disassembling the heat exchanger and identifying...

Read More...


MAY MONTHLY REPORT
by Edie Surprenant
Monday, 23 July 2007

MAY MONTHLY REPORT

Read More...


JUNE MONTHLY REPORT
by Edie Surprenant
Monday, 23 July 2007

JUNE MONTHLY REPORT

Read More...


FEBRUARY MONTHLY REPORT
by Edie Surprenant
Tuesday, 22 May 2007

FEBRUARY MONTHLY REPORT

Read More...


MARCH MONTHLY REPORT
by Edie Surprenant
Tuesday, 22 May 2007

MARCH MONTHLY REPORT

Read More...


APRIL MONTHLY REPORT
by Edie Surprenant
Tuesday, 22 May 2007

APRIL MONTHLY REPORT

Read More...


JANUARY MONTHLY REPORT
by Edie Surprenant
Monday, 2 April 2007

KRMA’S JANUARY HIGHLIGHTS

KRMA, Meccon, Tyson Engineering, and Strand Associates are working to clear up any remaining issues left open on the IEPA wastewater improvement project...

Read More...


DECEMBER MONTHLY REPORT
by Edie Surprenant
Monday, 19 February 2007

KRMA’S DECEMBER HIGHLIGHTS

Triple R Equipment completed the work on the DAFT #1 (Dissolved Air Floatation Thickener) in mid-December. They removed and replaced the existing skimmer...

Read More...


NOVEMBER MONTHLY REPORT
by Edie Surprenant
Thursday, 21 December 2006

KRMA's November Highlights

KRMA Staff continue to work with Meccon, Tyson Engineering, and Strand Associates to clear up any remaining issues left open on the wastewater treatment plant improvement project. ...

Read More...


OCTOBER MONTHLY REPORT
by Edie Surprenant
Tuesday, 5 December 2006

KRMA'S October Highlights

KRMA's OCTOBER HIGHLIGHTS

KRMA Staff continue to work with Meccon, Tyson Engineering, and Strand Associates to clear up any remaining issues left open on the wastewater treatment...

Read More...


KRMA Launches New Website!
by KRMA
Monday, 28 August 2006

Kankakee River Metropolitian Agency Information Online

Read More...